• If you're struggling to login because of the verification email not reaching you, don't worry it's just the forum settings applying the change slowly. I'll get in touch with those who are awaiting the verification email and sort your accounts out. I think new ones should go through fine now in most cases.

TF: Commissioning UFH after laying slate tilies

Currently reading:
TF: Commissioning UFH after laying slate tilies

A

ajn9000

TF: Commissioning UFH after laying slate tilies

I've had a look through threads but cannot find anything on this.
Lots of info on commissioning screed, but I can't find anything on post-screed-commissioning.
The question is: what would be the best UFH commissioining process after laying 10mm slate tiles? 10mm slate tiles on a solid 6mm adhesive bed, onto Mapai WP200.
They are laid onto a screed which has been thoroughly dried (text book heat stressed >12 months ago).
Q1: how long to wait to turn on UHF
Q2: how/when to increase UFH temp
Many thanks!

Commissioning UFH after laying slate tilies to Continue reading...